Colwick Loop Road/Daleside Road

Nottingham City Council has given details of the final stages of construction work on Daleside Road.

Listed below is the planned schedule for the final three weeks of works. There are no diversions, but we expect delays to Red 44/44A throughout.

  • Week 1: From Monday 12th February for 5 nights Mon-Fri (inclusive) 19:30-05:00. Remove existing surface.
  • Week 2: From Monday 19th February (Half Term) – 09:30-15:30 and 19:30-05:00. Tuesday 20th February to Friday 23rd February 09:30- 15:30 inclusive. Apply new surface course. Short sections of single file signal operation. Stops labelled Greyhound Stadium (CK02 and CK13) will not be served.
  • Week 3: On Sunday 25th February from 08:00 – 15:00 and between Monday 26th February to Thursday 1st March:  09:30-15:30. Apply new surface course. Short sections of single file signal operation. Stops labelled (CK02 and CK13) will not be served.

 

Affected services: 44 44A